Thursday, 2nd March, 2017
NATIONAL ASSEMBLY OF ZAMBIA
FIRST SESSION OF THE TWELFTH ASSEMBLY
ORDER PAPER - THURSDAY, 2ND MARCH, 2017
AT 1430 HOURS
QUESTIONS FOR ORAL ANSWER
128 Mr M Jere (Livingstone) - to ask the Minister of Local Government:
(a) when the construction of the Town Centre Market in Livingstone will be completed;
(b) what has caused the delay in completing the project;
(c) what the cost of the outstanding works is; and
(d) what the time-frame for the completion of the remaining works is.
129 Mr Ng’onga (Kaputa) - to ask the Minister of Justice:
(a) why judicial officers in Kaputa District report to the Luapula Provincial Administration instead of the Northern Provincial Administration; and
(b) when this anomaly will be rectified.
130 Mr Mung’andu (Chama South) - to ask the Minister of General Education:
(a) when the following schools in Chama South Parliamentary Constituency will be electrified to enhance the learning environment:
(i) Kamilala Boarding Secondary;
(ii) Chikwa Day High; and
(iii) Chitheba Day High;
(b) what the time-frame for electrifying each school is; and
(c) what the total cost of the project is.
131 Mr Kabanda (Serenje) - to ask the Minister of Health:
(a) when the Government will construct the following infrastructure at the new Serenje District Hospital:
(i) mortuary;
(ii) mothers’ shelter; and
(iii) kitchen;
(b) when beds will be procured for the Hospital; and
(c) when additional medical staff will be deployed to the Hospital.
132 Mr Kasandwe (Bangweulu) - to ask the Minister of Water Development, Sanitation and Environmental Protection:
(a) when the water reticulation project in Samfya District will commence;
(b) what has caused the delay in commencing the project; and
(c) what the estimated time-frame for the completion of the project is.
133 Mr Hamusonde (Nangoma) - to ask the Minister of Community Development and Social Welfare what measures the Government has taken to reduce the number of disabled persons begging on the streets of Lusaka.
134 Mr M Jere (Livingstone) - to ask the Minister of Youth, Sport and Child Development:
(a) when construction of a modern stadium in Livingstone will commence;
(b) what has caused the delay in commencing the project;
(c) what the time-frame for the completion of the project is; and
(d) what the estimated cost of the project is.
135 Mr Kasandwe (Bangweulu) - to ask the Minister of Housing and
Infrastructure Development:
(a) whether the Government has any plans to upgrade, to bituminous standard, the Kalubanshi-Milenge road in Bangweulu Parliamentary Constituency;
(b) if so, when the plans will be implemented; and
(c) if there are no such plans, why.
136 Mr Hamusonde (Nangoma) - to ask the Minister of Housing and Infrastructure Development:
(a) when construction works on the Mumbwa Road from Lumumba Road junction to Garden House Hotel will be completed; and
(b) what has caused the delay in completing the project.
137 Mr Kamboni (Kalomo Central) - to ask the Minister of Livestock and Fisheries:
(a) when an artificial insemination machine will be procured for the Artificial Insemination Centre in Kalomo District;
(b) what the cost of procuring and delivering the machine is; and
(c) what has caused the delay in procuring the machine.
______________________